On Saturday, February 21, volunteers Dwight, Colin, Dannis, Reid, Jerod and Paul started the day with warming up some equipment after an overnight low in the teens. Once the equipment started moving without any groans, we were able to gather some cross ties and get them placed along the ground prepared for track that we worked on last week. The gang then plugged the holes in the ties before gathering a bunch of tie plates to spread out. After a lunch break, we returned to dig out two sticks of rail and get them in place for future work to spike them down. We finished the day moving some more equipment around in the yard before calling it a day.
I have included a few pictures I was able to capture of the action today.
– Paul